Thames Water - High Street Roadworks

Published: 01 October 2020

With the completion of the works on Drayton Road, Thames Water will be looking to commencing the works on the High Street. However, their initial investigations earlier in the year discovered high water levels. This means that the work will need to take place in the summer months and work therefore will not be commenced until May 2021 at the earliest and this will be dependent on weather conditions over the summer. Their investigations also confirmed that due to the positioning and size of the pipe, this may need to result in a road closure. They have confirmed that given the time before works can proceed they have time to investigate whether there is a way for the works to be completed with traffic light control but they can make no assurances that this will be the case. We will keep you updated onto any further information on the same both in this newsletter and on the Parish Council website.